Writing a quote in Switzerland: content and commitment
A quote binds you until the deadline you set. Content, fixed price or estimate, 'without obligation', acceptance by e-mail: what the law says.
Updated on
In short. A quote binds you: if your customer accepts it within the deadline you set, the contract is concluded at your prices. So always state how long it is valid, and say clearly whether your price is fixed or estimated. Our free quote template prepares a complete quote, with its validity date, in two minutes.
Does a quote bind you?
Yes. Anyone who proposes a contract and sets a deadline for accepting it is bound until that deadline ends (art. 3 CO). If your customer says "agreed" on the last day, you must do the work at the price you quoted. A reply that reaches you after the deadline no longer binds you.
Without a written deadline, how long you are bound depends on how the quote was made:
- by phone or face to face, it must be accepted at once (art. 4 CO);
- by e-mail or post, you remain bound for as long as it normally takes for a reply to reach you (art. 5 CO): a few days for a simple job, longer for a complex quote. If a reply sent in time arrives late and you no longer want to be bound, tell your customer immediately.
That "normal time" is open to argument: a written deadline avoids it.
A quote can be withdrawn, but only if the withdrawal reaches the customer before the quote, at the same time, or before they have read it (art. 9 CO). By e-mail, that is rarely possible: once the quote is sent, expect to be bound until the deadline.
What your quote contains
- your details and your customer's;
- the date of the quote and a number, so you can find it again;
- what you are offering, line by line, with quantities and prices;
- the total, with VAT if you are registered for VAT;
- how long it is valid: "Quote valid until 15 December 2026";
- whether the price is fixed or estimated (see below);
- the payment terms of the future invoice, and any deposit.
Payment terms written in the quote your customer accepts are agreed with them, not set by you alone: that is what counts when the invoice is slow to be paid. If they depend on an event ("30 days after the site goes live"), record the date of that event in writing, for example in an e-mail to the customer. Our guide "Invoice payment terms" explains why.
Fixed price or estimate: what changes
| Situation | Fixed price (lump sum) | Estimate (approximate quote) |
|---|---|---|
| What you write | "Fixed price: CHF 4,800" | "Estimate: about CHF 4,800" |
| The planned work takes longer | You cannot charge anything more (art. 373 CO) | You charge the actual work (art. 374 CO) |
| The planned work takes less time | The customer still pays the lump sum | The customer pays the actual work |
| Large overrun | An increase is only possible through a court, in extraordinary and unforeseeable circumstances | The customer can withdraw from the contract, paying in principle for the work already done (art. 375 CO) |
The lump sum covers what the quote provided for. Extra work your customer asks for along the way (one more page, a change) is charged on top: have it confirmed in writing, with its price, before you do it.
With an estimate, the law does not say when an overrun becomes "excessive". Warn your customer as soon as the estimate is likely to be exceeded, and have them confirm the next steps in writing.
These rules apply to work you deliver (a website, a renovation, a logo): the Code sets them out for contracts for work. For a simple service with no promised result (advice, a course, coaching), they do not apply as they stand.
"Without obligation": what it is for
Writing "quote without obligation" frees you: you are no longer bound by your prices (art. 7 CO). When your customer says "agreed", they are making you an offer, which you remain free to accept. It is useful for a first idea of price, much less for a quote you want accepted. A price list or rates sent to everyone are not quotes, even without that wording.
How your customer accepts
The law requires no particular form (art. 11 CO): an "agreed" by e-mail, a signature on the quote or a yes on the phone concludes the contract. A written acceptance, even a simple e-mail, is still the safest: if you disagree later, it is your proof.
If your customer accepts but changes an important point (another price, another deadline), that is not an acceptance but a new offer: the contract is only concluded if you accept it in turn (art. 1 CO).
Example
On 15 November 2026 you quote for redesigning a website.
- Quote no. O-2026-012, valid until 15 December 2026.
- Design and build, fixed price: CHF 4,800.
- Copywriting, estimate: about 12 hours at CHF 95, so about CHF 1,140.
- 30% deposit on acceptance, balance payable 30 days after the site goes live.
Your customer accepts by e-mail on 10 December: the contract is concluded. If the design takes you two more days, the lump sum stays the same. If the copy takes 13 hours instead of 12, you charge 13 hours. If it needs much more, warn your customer before carrying on. And if they ask for one more page, have its price confirmed in writing.
What you may read elsewhere, and why it is wrong
- "A quote commits you to nothing until it is signed." Wrong: you, the author of the quote, are bound during the deadline; an acceptance by e-mail is enough.
- "A quote is valid for 30 days." Wrong: there is no statutory period. Without a written deadline, it binds you for the time a normal reply takes; with one, until it ends.
- "A quote can always be exceeded." Wrong: a lump sum covers the planned work whatever it costs you, and an estimate exceeded by a wide margin lets the customer withdraw.
- "You need a signed contract on top of the quote." Wrong: the accepted quote is the contract. A signed document is still good proof.
Write your quote now
- A complete quote, with its validity date: free quote template, PDF ready to send.
- All your quotes: in Yoda Bill, an accepted quote becomes an invoice in one click, with nothing to retype.
Sources
- Code of Obligations (English translation for information only), art. 1, 3, 4, 5, 7, 9, 11, 373, 374 and 375 (read on Fedlex on 15 November 2026)